ZoneConstruction DatesLocationDescription
Greater Lyttonsville / WoodsideBeginning on or about June 18th, 2018Lyttonsville Place BridgeBeginning on or about June 18th, 2018, the Lyttonsville Place Bridge will be closed for six months. An official detour for the closure is available here: http://www.purplelinemd.com/construction/2018/05/18/purple-line-transit-constructors-construction-update-lyttonsville-place-bridge-closure-beginning-on-or-about-june-18-2018/
Long BranchMay 23, 2018 - June 1, 2018Plymouth StreetFrom May 23 - June 1, 2018, crews will install geotechnical instrumentation targets along Plymouth St. Stakes will be placed to mark the destination of the targets.
University BoulevardOngoingW. Park Dr. - Temple St.Tree cutting and chipping activities continue eastbound along University Blvd between West Park Dr. and Temple St. Work will occur in the median. The eastbound left lane will have flagging operations to help assist drivers.
University BoulevardMay 9, 2018 - May 10, 2018Along University Blvd E. between 23rd Ave. and West Park Dr.Tree cutting and chipping activities will be occurring eastbound along University Blvd between 23rd Ave. and West Park Dr between 7 am and 5 pm. The service road and sidewalk on the eastbound side will have limited access and be closed to through traffic during this operation. A full-time flagger will be present to assist residents. No parking will be allowed in the work zone. Residents are asked to use the side streets for parking during this time frame.
Long BranchStarting May, 7, 2018Manchester PlaceCrews will begin drilling soldier piles on the southern wall of the current work zone at Manchester Place during regular construction hours from 7 am - 5 pm. No weekend work is planned.
Glenridge / New CarrolltonApr. 23, 2018 - May 7, 2018Veterans Parkway between Annapolis Rd. and Ellin Rd.Southbound lane closure - work continues along Veterans Parkway between Annapolis Rd. and Ellin Rd. This work requires a lane closure and flagging operation, which will occur from 9 am - 3 pm, Monday - Friday. Message boards are in place to alert pedestrians and vehicles of the new traffic pattern.
Silver SpringOngoingPatient First, at 16th Street YardDemolition continues on the Patient First in the 16th Street Yard, formerly known as the Spring Center during regular construction hours (7 am - 5 pm). No weekend work is planned.
Riverdale ParkStarting Apr. 16, 2018Mustang Dr. - Eastpine Dr.Tree clearing/grubbing and chipping continues east-bound along Riverdale Rd. between Mustang Dr. and Eastpine Dr.
University BoulevardOngoingW. Park Drive - Adelphi Rd.Prepatory work including silt fence installation, tree clearing/grubbing operations continue on University Blvd., from W. Park Dr - Adelphi Rd. Periodic lane closures may be required from 9 am - 4 pm.
University BoulevardOngoingRiggs Rd. - W. Park Dr.Prepatory work including silt fence installation, tree clearing and grubbing operations continue on University Blvd. Periodic lane closures may be required from 9 am - 4 pm.
Long BranchOngoingPlymouth StreetCrews will be working on Plymouth St. to install vibration monitoring devices. Flaggers will be on site to assist drivers in the area.
Bethesda / Chevy ChaseOngoingWoodmont PlazaConstruction work continues at Woodmont Plaza. The area will be fenced off to allow site preparation for future office trailers.
Bethesda / Chevy ChaseOngoingJones Mill Rd. through Rock Creek ParkTree removal and site preparation continues.
Long BranchOngoingArliss StreetUtility relocation work continues along Arliss Street. The utiltiy company will notify affected residents of any service interruptions.
Bethesda / Chevy ChaseOngoingConnecticut Ave. to Jones Mill Rd.Tree removal and site preparation continues.
Long BranchOngoingPlymouth StreetUtility relocation work continues along Plymouth St. The untility companies will notify affected residents of any service interruptions.
Long BranchNov. 20, 2017 - through 2021Plymouth StreetPlymouth Street is closed to non-local traffic between Bradford and Hartwell Roads to allow for the construction of the Purple Line's Manchester Station. The haul road and entrance to the construction site will be located on E. Wayne Ave.
Long BranchNov. 13, 2017 - through 2021Arliss StreetArliss Street is closed between Flower Ave and Walden Road. Access to local properties will be maintained.
Long BranchOngoingArliss StreetFor convenience, a new temporary driveway from Flower Avenue to the Giant Food Shopping center has been constructed.
Glenridge / New CarrolltonOngoingVeterans ParkwayWork continues along Veterans Parkway between Riverdale Rd. and Annapolis Rd. This work may cause periodic lane closures of the right hand southbound lane. Barriers are being placed to delineate the construction zone. Pedestrians and bicyclists are required to stay outside of the construction zone at all times.
Silver SpringOct. 1, 2017Future CCTThe CCT is currently closed to public access between Woodmont Ave. in Bethesda and Talbot Ave. in Silver Spring.
Greater Lyttonsville / WoodsideOct. 1, 2017Future CCTThe CCT is currently closed to public access between Woodmont Ave. in Bethesda and Talbot Ave. in Silver Spring.
Bethesda / Chevy ChaseOct. 25, 2017Future CCTThe CCT is currently closed to public access between Woodmont Ave. in Bethesda and Talbot Ave. in Silver Spring.