The Maryland Department of Transportation Maryland Transit Administration’s (MDOT MTA) Purple Line Project (Project) DBE Program is committed to supporting MDOT certified DBEs to perform meaningful services in the design and construction phases along the project alignment. As the Project continues to progress, so have the significant contributions of participating DBE subcontractors.

The Project tracks payments towards disadvantaged, minority, women, small, and disabled-owned business. Additionally, from those payments, eligible payments that can be counted towards the DBE Goals are reflected in the following charts:

Design Phase
DBE Goal (%) DBE Commitments ($) DBE Commitment (%) Payments Counted Towards Goal DBE Goal Achieved (%)
26% $45,901,873.59 28.33% $51,025,970.78 31.49%
Construction Phase
DBE Goal (%) DBE Commitments ($) DBE Commitment (%) Payments Counted Towards Goal DBE Goal Achieved (%)
22% $556,916,534.41 17.47% $298,041,743.71 9.35%

*Figures represent the most recent data available through February 2024 and were prepared for web publishing April 2024.

DBE Impact in Numbers

Below are the current programmatic figures highlighting DBE performance and participation measures on the Purple Line Project.

The following figures represent the most recent data available through February 2024 and were prepared for web publishing April 2024. Click any of the below charts to view an enlarged version.

Disadvantage Business Enterprise Participation by Maryland County (Design)

DBE Participation by MD County (Design)

Disadvantage Business Enterprise Participation by Maryland County (Construction)

DBE Participation by MD County (Construction)

Disadvantage Business Enterprise Participation Commitments by Ethnicity (Design)

DBE Commitments by Ethnicity (Design)

Disadvantage Business Enterprise Participation Commitments by Ethnicity (Construction)

DBE Commitments by Ethnicity  (Construction)

Disadvantage Business Enterprise Participation by Month

DBE Participation by Month

DBE Participants

Since 2016, the contributions of DBE subcontractors have been instrumental in advancing the ongoing development of the Project's alignment. To date, we are proud to acknowledge that over 195 DBEs have actively contributed to the progress of the Purple Line Project with design and construction services. We value and appreciate the collaborative efforts that contribute to the success of the Purple Line Project and remain committed to furthering our partnership with DBEs in this endeavor.